The Arab Gas Pipeline is Back—in a New Guise

The Arab Gas Pipeline is Back—in a New Guise

2026-09-09
2847 view

Efforts to supply Lebanon with natural gas via Jordan and Syria have entered a new phase, as the Jordanian government agreed on September 6 to supply Lebanon with natural gas sourced via a vessel moored at the Port of Aqaba, in cooperation with Damascus, and aimed at improving Lebanon’s patchy electricity supply.

Under the new arrangement, Jordan is to import liquefied natural gas (LNG) from global markets and re-gasify it via a floating regasification unit and existing infrastructure at the Red Sea port of Aqaba. The gas will then be transported northward through the Jordanian gas network and transferred to Lebanon via Syrian territory. This is a departure from the project’s original format, which envisaged transporting Egyptian gas to Lebanon via the Arab Gas Pipeline.

The Jordanian decision follows months of technical consultations and meetings among Jordanian, Syrian, and Lebanese officials, as well as progress in reactivating the region’s gas supply route. It also comes as Lebanon seeks more stable and cost-effective fuel sources for its power plants, amidst an ongoing energy crisis and a pressing need for are more reliable electricity supply over more hours of the day.

The Arab Gas Pipeline had long been seen as one of the region’s most significant energy infrastructure projects. It was established to link Egypt, Jordan, Syria and Lebanon via a natural gas transmission network, linking Al-Arish in Egypt, to Aqaba and onwards into Jordanian then Syrian territory, finally terminating in Lebanon.

In 2003, the pipeline facilitated gas operations and exchanges among several countries in the region. In 2012, the revolution in Syria disrupted the project, and certain Syrian facilities—including transmission lines, transformer stations and associated facilities—sustained significant damage. Security conditions and international sanctions also introduced political, technical and financial complexities that prevented the resumption of regular operations.

Between 2021 and 2022, efforts to revive the route resumed, with the aim of supplying Lebanon with Egyptian gas via Jordan and Syria, to power the Deir Ammar plant. Although agreements and technical plans were prepared, the project did not materialize into regular supplies. This was due to several factors, including financing difficulties, sanctions against Syria, the lack of technical readiness in certain parts of the network, and Lebanon’s dire financial situation.

The current approach differs from these earlier attempts in that it does not rely exclusively on Egyptian gas. Instead, it leverages Jordan’s location and existing infrastructure in Aqaba to receive liquefied natural gas (LNG) from global markets, re-gasify it and transport it via the pipeline network to Syria and Lebanon.

This year has seen serious moves toward rebuilding a regional gas corridor. Jordan began supplying Syria with natural gas, utilizing the Aqaba infrastructure and the transmission network extending into Syrian territory.

As the three nations have continued to coordinate, the initiative has moved from the concept of restarting the old pipeline to a more flexible model based on using LNG imported via Jordan. In May 2026, Jordan, Syria and Lebanon unveiled a trilateral gas cooperation agreement, as part of broader efforts to secure energy supplies and reactivate regional transport networks.

All this led to the understandings announced by Jordan on September 6. Yet the gas has not automatically started being pumped to Lebanon. Technical, contractual and operational steps remain to be completed before supplies actually reach the Deir Ammar power plant. Consequently, the current situation marks a shift from pipeline rehabilitation feasibility studies to the formulation of clear implementation arrangements.

The Lebanese track will require ticking several technical and contractual boxes, notably rehabilitating sections of the pipeline leading to the plant, as well as verification of the integrity of the segments traversing Syrian territory.

Furthermore, the parties must reach a final agreement over gas volumes and prices, payment and transit mechanisms, and operational responsibilities. These issues are particularly critical for Lebanon, in light of its ongoing financial crisis and the need for a sustainable payment mechanism that prevents gas supplies from becoming an additional financial burden on the state.

From a technical standpoint, the delivery of gas to Lebanon does not depend solely on Jordan’s readiness. The entire route hinges on the integrity of the Syrian network and its capacity to transport the required volumes, as well as Lebanon’s ability to receive the gas and utilize it at the Deir Ammar power plant.

The upcoming phase will likely focus on completing technical work in both Lebanon and Syria, finalizing commercial agreements and defining volumes and timelines, prior to moving on to operational testing and starting pumping gas.

Should this phase succeed, the gas could provide the Deir Ammar plant with a better supply of fuel suited to its efficient operation, thereby helping increase electricity generation and increasing the hours of supply. In the medium term, the Aqaba route could evolve into a broader platform for regional energy trade, particularly if the nations involved can successfully establish stable arrangements regarding transit, pricing, payments and maintenance. This could eventually integrate with regional electricity interconnection and energy exchange projects.